Lidl Reional Depot

Bespoke retaining wall installation

Lidl regional depot project

Over 1km of retaining wall was required to make space for a new 630,000 square ft Regional Distribution Centre in Motherwell, Scotland. The £70 million project to build Lidl’s largest regional distribution warehouse in Britain was awarded to Winvic Construction, with the retaining walls to be manufactured by FP McCann.

0 m
Retaining Walls
0
Crane Lifts
0
Days Installation
0 m
Max Wall Height

We were asked to take on the management of the cast-in retaining wall installation and foundation pours.

Our team was responsible for coordinating the precast deliveries and retaining wall off-load. Our appointed person prepared the relevant lifts plans and RAMS, and oversaw all precast lifting onsite.

See our Precast Concrete in action

Not everyone’s a precast concrete expert – and it can be hard to find the right product for your project. Here is a selection of recent projects that show you what our precast products can be used for.

Scroll to Top